Technip Energies Awarded a Significant Contract by Neste for Renewable Products Refinery Expansion in Rotterdam

Technip Energies has been awarded a significant contract by Neste for the expansion of their renewable products production capacity in Rotterdam, the Netherlands, as part of the existing Partnership Agreement between Technip Energies and Neste.

The contract covers Engineering, Procurement services and Construction management (EPsCm) for the expansion of Neste’s existing renewables refinery in Rotterdam which will increase Neste’s overall renewable product capacity by 1.3 million tons per year.

This contract follows the Front-End Engineering and Design (FEED) delivered by Technip Energies in 2021.

The production process is based on Neste’s proprietary NEXBTL™ state-of-the-art technology, which allows the conversion of renewable waste and residue raw materials like used cooking oil and animal fat waste into renewable fuels.

Bhaskar Patel, SVP Sustainable Fuels, Chemicals and Circularity of Technip Energies, stated: “We are pleased to be entrusted once again by Neste for the expansion of their renewable products production platform in Rotterdam. This award relies on our long-term collaboration, illustrated by the successful delivery of two world-scale renewable productsrefineries in Rotterdam and Singapore and the ongoing expansion project of Neste’s renewable products refineryin Singapore.We are committed to make this project a success as we share a common vision of accelerating the transition towards a sustainable future, using technological advancement as a key lever.”

Source: Technip Energies

Technip Energies Awarded a Large EPC Contract by Hafslund Oslo Celsio for a World-First Carbon Capture and Storage Project at Waste to Energy Plant in Norway

Technip Energies has been awarded a large Engineering, Procurement, Construction (EPC) contract by Hafslund Oslo Celsio, the largest supplier of district heating in Norway, for a world-first carbon capture and storage (CCS) project at waste to energy plant located in Oslo, Norway.

The project will be the first full-scale waste-to-energy plant in the world with CO2 capture. 400,000 tons per year of CO2 will be captured, which is the equivalent of the emissions from around 200,000 cars and will reduce Oslo’s emissions by 17%. As part of the Longship project, the COwill then be liquified and exported to Northern Lights which is the first cross-border, open-source CO2 transport and storage infrastructure network.

The Carbon Capture plant will use the Shell CANSOLV® CO2 Capture System, a state-of-the-art amine based technology for the capture of CO2 from the flue gas.

This EPC contract award follows several years of a joint journey with the completion of the design competition, the successful delivery and test of a pilot unit and continuous collaboration between Technip Energies and Hafslund Oslo Celsio to optimize project economics. Developing, testing and proving this cost-effective solution is the result of a close partnership and co-development with the owner, T.EN and the technology provider.

Arnaud Pieton, CEO of Technip Energies, commented: “We are proud to be entrusted by Hafslund Oslo Celsio to support the development of the first waste-to-energy with Carbon Capture and Storage project in the world. Norway is at the forefront of decarbonization initiatives and, by being part of Hafslund Oslo Celsio project, we will contribute to one of the two projects of Longship, the very first Phase of Northern Lights. We are committed to leverage our strong expertise in CO2 management, our local presence and our alliance with Shell to successfully deliver this groundbreaking project, a key milestone towards a low-carbon future.”

Source: Technip Energies

Technip Energies and Saulsbury Industries Awarded EPC Contract for Carbon Capture & Storage at ExxonMobil LaBarge, Wyoming, US Facility

Technip Energies, in Consortium with Saulsbury Industries, has been awarded a contract for the Engineering, Procurement and Construction (EPC) to expand the carbon capture and storage (CCS) at ExxonMobil’s LaBarge, Wyoming facility.

The LaBarge plant has already captured more CO2 than any other facility in the world. The plant has capacity to capture more than 6 million metric tons per year, and this expansion project will enable the capture of more than one million additional metric tons of CO2 per year.

The expansion will consist of a modification of the existing gas treatment facility to increase the carbon capture capacity and the installation of pipeline to transport the COto the reservoir where it will be stored. Technip Energies will be responsible for the engineering and procurement services, while Saulsbury Industries will perform construction and the pipeline installation.

Laure Mandrou, Senior Vice President Carbon-Free Solutions of Technip Energies, commented: “We are very pleased to be working with ExxonMobil to expand the CCS at LaBarge, the world’s largest carbon capture facility. We are committed to advancing the energy transition and this project will be a hallmark in reducing carbon emissions.”

Dan Ammann, President of ExxonMobil Low Carbon Solutions, stated: “The expansion of carbon capture and storage capacity at LaBarge underscores ExxonMobil’s commitment to advancing lower-emissions technologies with projects around the world. Carbon capture and storage is necessary to help meet society’s net-zero goals and, with the right policies in place, the technology can be broadly deployed immediately.”

Dennis Chismar, Senior Vice President of Saulsbury Industries, stated: “We are pleased to be collaborating with Technip Energies and supporting this exciting project with ExxonMobil. Our commitment to assisting in the reduction of carbon emissions and being a key contributor to the LaBarge expansion project marks a proud and historic moment for Saulsbury.”

Source: Technip Energies

Technip Energies Awarded a Substantial Petrochemical Contract by Borouge in the UAE

Technip Energies has been awarded a substantial(1) Engineering, Procurement, and Construction (EPC) contract in consortium with TARGET Engineering by Abu Dhabi Polymers co. Ltd. (Borouge), a joint-venture between ADNOC and Borealis, for the construction of a new Ethane Cracker Unit, to be integrated in the Borouge 4 petrochemical complex in Ruwais, UAE.

The contract was signed by H.E Dr. Sultan Al Jaber, Minister of Industry and Advanced Technology, Managing Director and Group CEO of ADNOC and Chairman of Abu Dhabi Polymers Co Ltd. (Borouge), and Technip Energies CEO Arnaud Pieton, in presence of His Highness Sheikh Mohamed bin Zayed Al Nahyan, Crown Prince of Abu Dhabi and Deputy Supreme Commander of the UAE Armed Forces, and Chairman of the Board of Directors of the Abu Dhabi National Oil Company (ADNOC) and the President of the French Republic, Emmanuel Macron during the French delegation’s visit to the UAE.

This EPC contract covers the delivery of a new Ethane Cracker Unit, in excess of 1,500 KTA(2), based on proprietary Technip Energies technology. The new Borouge 4 complex will be located in the Ruwais Industrial Area in Abu Dhabi. It is considered as one of the major strategic projects to enable ADNOC to meet its target growth, which would sustain its current market share in the growing polyolefin market.

This award follows the successful execution of FEED(3) competition, reflecting Technip Energies’ selective approach to be involved at a very early stage of any development and TARGET growth strategy to cooperate with major international contractors for projects in the country.

Arnaud Pieton, CEO of Technip Energies, stated: “We are extremely honored to have been selected by Borouge both as technology provider and EPC contractor and reconfirms Technip Energies long-standing leadership in ethylene and technology integration projects execution. This award also represents an appreciation of our strong historical presence in Abu Dhabi for over four decades and our commitment to enhance In-Country Value. The Borouge team competencies and knowledge of olefins plants together with Technip Energies expertise in technology and projects execution led to effective design and optimized project economics.We will also evaluate the carbon footprint of the Borouge 4 Ethane Cracker in order to minimize future COemissions, reflecting Borouge and Technip Energies ambition to accelerate the transition towards a low-carbon future.”

  1. A “substantial” award for Technip Energies is a contract award representing between €500 million and €1 billion of revenue.
  2. KTA: kilo tons per annum.
  3. Front End Engineering and Design.

Source: Technip Energies