Air Liquide and TotalEnergies partner to develop low-carbon hydrogen production in the Normandy industrial basin

Air Liquide and TotalEnergies are joining forces to decarbonize hydrogen production at TotalEnergies’ Normandy platform in France. This project will enable in time the supply to TotalEnergies by Air Liquide of low-carbon hydrogen by relying on Air Liquide’s hydrogen network in Normandy and the implementation of a large-scale CO2 capture and storage solution (CCS). In line with the objective of both companies’ to reach carbon neutrality by 2050, this ambitious project is part of a sustainable development approach which will help develop a low-carbon hydrogen ecosystem in the “Axe Seine/Normandy”, progressively supported by technologies such as CCS and electrolysis.

Reducing Carbon Emissions

Under a long term contract agreement, Air Liquide will take over and operate the 255 tons-per-day hydrogen production unit at the TotalEnergies platform in Normandy. Connecting the unit to Air Liquide’s hydrogen network will enable to optimize its performance and, ultimately, develop the world’s first low-carbon hydrogen network. The network already includes a hydrogen production facility in Port-Jérôme equipped with Air Liquide’s CryocapTM carbon capture solution since 2015. Air Liquide is considering adding a large-scale unit to produce renewable hydrogen via electrolysis.

In addition, the companies will launch development studies to deploy a carbon capture and storage (CCS) project to decarbonize the hydrogen produced in this unit at the Normandy platform. Air Liquide would install its Cryocap™ process to capture CO2, while TotalEnergies would handle transportation and storage of the captured CO2, notably through the Northern Lights (Norway) and Aramis (Netherlands) CCS projects being developed in the North Sea.

In the long term, the implementation of these projects would reduce the carbon emissions from the unit’s hydrogen production by approximately 650,000 tons of CO2 per year by 2030.

Decarbonizing the Normandy Industrial Basin

This cooperation between Air Liquide and TotalEnergies is aligned with their shared ambition to help decarbonize industrial operations in the “Axe Seine/Normandy”. Along with other industrial companies, the partners signed a Memorandum of Understanding announced in July 2021, to develop carbon capture and storage infrastructure in Normandy with the goal of reducing CO2 emissions by up to 3 million tons per year by 2030.

François Jackow, Executive Vice President and a Member of the Air Liquide Group’s Executive Committee supervising Europe Industries activities, said:

“Decarbonizing industry is a major challenge. The large range of solutions we have developed enable us to support our customers in their path towards energy transition. We have worked with TotalEnergies for many years, and are pleased to strengthen our partnership today with the deployment of solutions that will provide the Normandy industrial basin with a low-carbon hydrogen network in the years ahead. In line with our objective to reach carbon neutrality by 2050, Air Liquide is acting now to develop low-carbon and renewable hydrogen production and build a more sustainable future.”    

Bernard Pinatel, President, Refining & Chemicals and Member of the Executive Committee of TotalEnergies, said:

“This planned investment at our Normandy platform will enhance its industrial competitiveness and secure its long-term future. We are delighted to partner with Air Liquide on low-carbon hydrogen projects so we can work together on reducing the carbon emissions from our industrial operations. These projects contribute to the collective effort launched in the Le Havre industrial zone and the Seine corridor. This is fully aligned with TotalEnergies’ ambition to get to net zero emissions by 2050.”

Under French law, the proposed transfer of the hydrogen production unit to Air Liquide is subject to the process for notifying and consulting employee representatives of the TotalEnergies Normandy platform, and to the approval from the competent authorities.

Source: Air Liquide

TotalEnergies signs major agreements for the sustainable development of the Basra region natural resources in Iraq

TotalEnergies, the Iraqi Ministries for oil and electricity, and the country’s National Investment Commission have signed, in the presence of the Prime Minister of Iraq, major agreements covering several projects in the Basra region, designed to enhance the development of Iraq’s natural resources to improve the country’s electricity supply. Iraq, a country rich in natural resources, is indeed experiencing electricity shortages while it faces a sharp increase in demand from the population.

TotalEnergies, with the support of the Iraqi authorities, on the one hand will invest in installations to recover gas that is being flared on three oil fields and as such supply gas to 1,5 GW of power generation capacity in a first phase growing to 3 GW in a second phase, and, on the other hand, will also develop 1 GWac of solar electricity generation capacity to supply the Basra regional grid.

These agreements include: 

  • The construction of a new gas gathering network and treatment units to supply the local power stations, with TotalEnergies also bringing its expertise to optimize the oil and gas production of the Ratawi field, by building and operating new capacities.
  • The construction of a large-scale seawater treatment unit to increase water injection capacities in southern Iraq fields without increasing water withdrawals as the country is currently facing a water-stress situation. This water injection is required to maintain pressure in several fields and as such will help optimizing the production of the natural resources in the Basra region.
  • The construction and operation of a photovoltaic power plant with a capacity of 1 GWp to supply electricity to the grid in the Basra region.

 These projects represent a total investment of approximately $10 billion (100% share).

“These agreements signal our return through the front door to Iraq, the country where our Company was born in 1924. Our ambition is to assist Iraq in building a more sustainable future by developing access to electricity for its people through a more sustainable use of the country’s natural resources such as: reduction of gas flaring that generates air pollution and greenhouse gas emissions, water resource management and development of solar energy,” said Patrick Pouyanné, TotalEnergies’ Chairman and CEO.“This project perfectly illustrates the new sustainable development model of TotalEnergies, a multi-energy Company which supports producing countries in their energy transition by combining the production of natural gas and solar energy to meet the growing demand for electricity. It also demonstrates how TotalEnergies can leverage its unique position in the Middle East, a region where the lowest-cost hydrocarbons are produced, to gain access to large-scale renewable projects”, he added.

Source: TotalEnergies

KOC---WorleyParsons

Worley lands FEED contract for Total’s 20,000 psi North Platte field development

Worley has been awarded the Front-End Engineering Design (FEED) contract for TOTAL E&P USA’s North Platte field development in the Gulf of Mexico.

Located approximately 275 kilometers off the coast of Louisiana, the North Platte field development includes a semi-submersible floating production unit (FPU) in water over 1,300 meters deep.

The project brings together Worley’s recently acquired capability for the floating production unit topside design with Intecsea experience for the design of the hull, mooring and subsea pipelines. Now under one roof, Worley’s expanded capability to deliver flexible floating production unit designs with capital efficiency and minimal time to market proved a key contributor to this award.

Having completed the pre-FEED phase in August 2019, this award extends Worley’s involvement in Total’s deepwater Gulf of Mexico project.

“We are delighted to continue supporting Total’s return to Gulf of Mexico operations through the North Platte development,” said Karen Sobel, Group President for Major Projects and Integrated Solutions at Worley.  “This project provides Worley with an opportunity to bring together our complimentary capability in both topside and hull design to offer complete, capital efficient and lightweight deep-water solutions. It’s an exciting prospect for our customers and our business.”

The FEED component of the project is being led by Worley’s Houston office with support from its Hyderabad office in India.

The North Platte Development forms part of Total’s reentry, as an operator, into Gulf of Mexico operations with oil production expected to average 75,000 bpd at plateau level.

TOTAL expects to make its final investment decision in 2021.

Source: http://bit.ly/3aDjvbc